December 17, 2011

Triggering the Process Chains at Particular Date using Events

This article describes how to run the Process Chain at particular Dates using Events. The requirement is every month we need to load the data (or Trigger the Process chain) on 8th and 11th day.

•This logic is useful in different scenarios also; here I’m taking Process Chain Scenarios.
•Using this logic, you can also automate some Programs/Function Modules etc...

Triggering the Process Chains at Particular Date using Events

No comments: